City HallTop story
Noblesville has been selected for nearly $10 million in federal money to make Greenfield Avenue safer
The Greenfield Avenue plan adds a roundabout, a bridge, trails and more
| Piece | What's planned |
|---|---|
| Roundabout | Greenfield Ave. and 16th St. |
| Bridge | New, over the Elwood Wilson Drain |
| Trails | 10-foot-wide, both sides |
| Also | Lighting, markings, signage, drainage |
Source: Fox 59
If you drive Greenfield Avenue, a roundabout is in the plans. Noblesville has been selected for federal Safe Streets money, and the city said in a news release that its Safer Greenfield Avenue Project will "transform approximately half a mile of roadway."
- Grant: $9.9 million, Safe Streets and Roads for All
- Project cost: $15.1 million
- Stretch: South 10th to South 16th streets
- Next: city and USDOT finalize grant agreement before funds are obligated
“Greenfield Avenue is an important corridor for our community, particularly for families traveling to and from Stony Creek Elementary School.”
Noblesville Mayor Chris Jensen
The release says the proposed roundabout is "projected to significantly reduce crash rates." Jensen also thanked U.S. Sens. Todd Young and Jim Banks for supporting the project.
The federal grant covers most of the $15.1 million project
$9.9 millionFederal grant for the Safer Greenfield Avenue Project
Source: Fox 59
View as table
| Value | |
|---|---|
| Federal grant for the Safer Greenfield Avenue Project | $9.9 million |
| Total project cost | $15.1 million |